Define a common scope before inviting quotations
Send the same functional duty, operating envelope, site utilities, environment, integration interfaces, safety and documentation requirements to every bidder. Give each requirement a status: mandatory, preferred or informational. A mandatory technical or legal failure is a gate, not something to offset with a low price score.
| RFQ requirement family | What the supplier must state | Evidence example |
|---|---|---|
| Duty and performance | Rated range, normal and upset case, efficiency/throughput, assumptions | Datasheet, sizing calculation and guarantees |
| Controls and integration | Signal list, protocols, security roles, interfaces and data ownership | I/O list, protocol map and architecture diagram |
| Safety and compliance | Applicable standards, certificates, limits and responsibility split | Compliance matrix and certificate scope |
| Installation / startup | Included engineering, hardware, FAT/SAT, training and exclusions | Scope split, test protocol and rate schedule |
| Support and lifecycle | Warranty, response time, software licenses, spare parts, obsolescence | Support SLA and 5-year cost schedule |
| Commercial exposure | Currency, taxes, Incoterms, delivery, payment and change-order basis | Signed quotation and terms |
Worked example: evaluate five-year cash cost
Consider two fictional offers for the same qualified system. Vendor A quotes €42,000 equipment, €8,000 integration, €2,000 annual license/support and €3,000 estimated five-year spare parts. Vendor B quotes €47,000 equipment, €5,000 integration, €500 annual support and €4,000 spares.
Illustrative undiscounted five-year totals are Vendor A: €63,000 (42,000 + 8,000 + 5×2,000 + 3,000) and Vendor B: €58,500 (47,000 + 5,000 + 5×500 + 4,000). Vendor B has the higher hardware quote yet the lower five-year figure in this limited example. Neither offer is preferable until technical compliance, risk, payment timing and scope exclusions are assessed.
A defensible selection sequence
- Compliance gate. Eliminate or formally resolve offers failing mandatory function, safety or site constraints.
- Technical normalisation. Record all deviations and price missing scope with the same assumptions for every bidder.
- Commercial normalisation. Compare the same currency, delivery boundary, tax scope, payment timing, licenses and warranty duration.
- Lifecycle model. Include energy, consumables, maintenance labor, spares, planned upgrades, software and likely downtime impacts when evidence exists.
- Risk review. Examine references, cyber and service responsibility, delivery dependency, geographic support and change-control terms.
- Decision record. Save assumptions, source documents, exclusions, conflicts of interest, selected option and accountable approvals.