Start with the production model, not a vendor shortlist
Make-to-stock, make-to-order, assemble-to-order and engineer-to-order businesses have different planning needs. A manufacturer dealing with frequent engineering changes, serial traceability and quality holds should not assume that software optimized for repeat standard assemblies will handle its exceptions. Write representative business scenarios before collecting demos.
The six evidence gates
- Bill of materials and revisions: can the application maintain multilevel BOMs, approved alternates, effectivity and engineering changes without overwriting history?
- Capacity and scheduling: distinguish infinite-capacity MRP calculation from finite-capacity sequencing. Ask vendors to demonstrate the effect of a machine outage and an urgent order.
- Inventory and traceability: test lot/serial genealogy, quality quarantine, backflushing, physical count and supplier certificate links.
- Financial and commercial integration: test quotations, purchasing, cost roll-ups, invoicing and integrations, including ownership of master data.
- Shop-floor adoption: try the real operator journey, including rework, scrap, nonconformity and offline interruptions.
- Security and exit: obtain contractual answers about access roles, backup, audit trails, data export, incident response and retention before committing.
Sample weighted scorecard
Decide minimum mandatory gates first. Then score each criterion 0–5 from a witnessed demonstration or documented evidence, not a marketing claim. Multiply each score by its weight. A mandatory safety or regulatory gap should disqualify a supplier even if the weighted score is high.
| Criterion | Example weight | Evidence required |
|---|---|---|
| Production fit and BOM revisions | 25% | Live scenario using representative order |
| Planning and capacity | 20% | Outage and expedite scenario |
| Traceability and quality | 20% | Genealogy and nonconformity trial |
| Integrations and export | 15% | API/export proof and data ownership |
| Implementation and support | 10% | Named plan, milestones and support model |
| Total lifecycle cost | 10% | 3-year cost breakdown incl. migration |
How to calculate the weighted result
If a supplier scores 4, 3, 5, 2, 4 and 3 out of five for the six criteria, the weighted total is 3.60/5: 0.25×4 + 0.20×3 + 0.20×5 + 0.15×2 + 0.10×4 + 0.10×3. This is a mathematical example only, not a PROFENG rating of any supplier.
Fit and non-fit indicators
MRP-oriented software may fit a smaller discrete manufacturer that wants purchasing, stock, bills of material and production orders in one system. It may not fit on its own when advanced finite-capacity optimization, complex multi-plant quality or extensive regulated validation is required. For those cases, investigate APS, MES, quality systems and specialist integrations as separate scope items rather than assuming one suite performs every function.
Partner links and commercial independence
PROFENG lists some manufacturing software vendors through commercial programmes. MRPeasy is one relevant vendor to assess, not a preselected winner. Referral arrangements may generate commissions; selection criteria and the example scorecard above do not use referral rates. See the partner directory and affiliate disclosure. No comparative product testing or vendor verification is implied by this example.
Method, accuracy and limitations
Examples on this page are derived from the stated equations and chosen example inputs; they are not evidence that PROFENG tested a real industrial installation. Confirm the governing project specifications, manufacturer data, local codes and professional review before design or commissioning. See calculation methodology, engineering limitations and report an error.