FAT and SAT for PLC, DCS and SCADA: prove each claim with evidence

A checklist is not the same as an accepted system. Use this structured test map to distinguish software demonstration, instrument-loop tests, site integration and documented safe handover.

7 November 2026 · Reference workflow, not an approved site test procedure

Start with the test basis, not with the HMI

Before testing, freeze a reviewed revision of the functional design specification, I/O list, cause-and-effect matrix, alarms, communications map, network architecture, user-access roles and test protocol. Every test has an identifier, prerequisite, expected result, observed result, evidence link, deviation and responsible signoff.

StageTest activityEvidence to retainTypical failure often missed
Design traceabilityMap each requirement to a test caseApproved spec revision, requirement ID, test IDAcceptance criteria are vague or changed after execution
Digital input and outputProve normal and abnormal states, polarity, fail stateI/O tag, channel, injected/simulated state, controller diagnosticsNormally-closed contact interpreted as normally-open
Analog inputCheck lower, mid and upper engineering values and diagnosticsCalibrator value, raw channel, DCS tag, HMI and trendDuplicate scaling, wrong unit, stale historian tag
Interlocks / permissivesProve demand, inhibition, reset and failure behavior under approved test controlsCause/effect trace, state screenshots, signed permitsPermissive only checked in the happy path
HMI / alarmsVerify descriptions, severity, units, acknowledge behavior and navigationAlarm list revision, timestamped screenshots, test notesTag mismatch or inconsistent alarm priority
CommunicationsCheck mapping, quality, timeout, stale-value handling and restartProtocol map, register/address trace, event logValue remains apparently valid after link loss
Access / recoveryCheck role permissions, backup/restore and time synchronizationAccess matrix and restore evidenceEngineer changes available to operator accounts
SAT / handoverRepeat integration-critical tests with installed instruments and actual equipmentAs-left config, punch list, redlines, signoffsFAT simulation mistakenly accepted as field evidence

Example: a valve close permissive

Suppose a motorised valve is only allowed to close while a transfer pump is stopped. A meaningful test covers the expected permissive satisfied state, a running-pump blocked demand, loss of pump-running feedback, valve travel timeout and operator acknowledgement. The correct reaction to loss of feedback is not guessed: it must match the approved cause-and-effect design and applicable safety analysis.

Document the test's initial plant state, the exact signal being stimulated, controller state changes, actuator response and restoration. If a test uses simulation rather than physical movement, mark that distinction explicitly and ensure a site test still covers the required physical path.

Test record template

Test IDRequirement / tagPrecondition & stimulusExpectedObserved / evidenceDisposition
FAT-AI-001PT-101 / analog inputApproved simulation at 12 mA for 0–16 bar8.00 bar, within project toleranceRecord raw counts, DCS tag, HMI, screenshotPass only after documented measurement
FAT-COM-001Protocol healthApproved temporary comms lossQuality/fallback per designRecord timeout and alarm timestampsOpen deviation if behavior differs

Close-out rules

  1. Classify defects by impact, including safety, functional loss, data integrity and usability.
  2. Log changes against controller/HMI version and test revision; retest affected interfaces.
  3. Preserve open punch-list entries, compensating controls and accountable owners; never erase them to improve a pass rate.
  4. Confirm backups, restoration, cyber access, time sync, loop reinstatement, and operator training before handover.

Reference

ISA-5.1 helps establish consistent instrument identification. It does not replace safety lifecycle standards, site-specific FAT/SAT specifications or legal requirements. For analog loops, use the 4–20 mA worked guide.

Critical restriction

Safety instrumented functions, emergency shutdown logic and protective interlocks require an authorized, project-specific test procedure and qualified personnel. This public checklist does not certify SIL, functional safety or regulatory compliance.